Why Buhari can’t complete Abuja -Kaduna-Kano expressway – Fashola

The Minister of Works and Housing Mr Babatunde Fashola says the Abuja-Kaduna- Kano Expressways will be completed by April 30.

Fashola said this at the pre-inspection of the completed Loko-oweto Bridge in Nasarawa State on Wednesday.

He said the Abuja-Kano expressway was the biggest of all the road projects in terms of scope and budget.

“Abuja-Kano is the biggest of the three projects in terms of scope, in terms of size, in terms of budget; it is 375 kilometres.

”It encompasses 41 bridges of different sizes. It was the last to start, so it cannot finish at the same time. That is the honest truth.

“But we have made progress from Zaria to Kano, that is, 137 kilometres, and the contractors tell us that by May 15  that site should be fully completed.

“Then, we have Kaduna to Zaria, which is about 70 kilometers away. That side of course, they say will be completed on the 30th of this month, fully open to traffic,” he said.

Fashola, however, said Abuja-Kaduna road which is one of the projects embarked upon by the Buhari administration, would not be  finished in the life of the  administration

“The eye of the storm, the most difficult part and that is the busiest part, is the Kaduna to Abuja side. That has suffered all kinds of delays and it would not be finished in the life of this administration.

“It is the most trafficked side. It has almost 40,000 vehicles in the traffic every day. But those are not just the problems; the problems are that the right of way has been severely encroached on between FCT, Niger and Kaduna states.

“We are working with the governors to help relocate all the obstructions, otherwise, we cannot fully build it.

“Apart from that, the project is also delayed by the Ajaokuta-Kaduna-Kano gas pipeline project. We need that gas pipeline project as a major boost for our energy security.

The minister said these were  some of the challenges unseen to members of the public, adding that both the road and the pipeline were important hence they had to be taken in sequence and order.

“We lost almost a year and a half to security challenges or sometimes contractors had to move from that section completely – they could not work.

“Thankfully, we must acknowledge the work that has been done by the law enforcement agencies, especially the Chief of Defense Staff and his team.

“They have made the return to that site easier and possible for our contractors. So, those are no longer an existent problem now. It is just the manhours now to do the work,” he said.